EVALUACIÓN DE LA EFICACIA DE LA APLICACIÓN DE LAST PLANNER SYSTEM EN UN PROYECTO DE CONSTRUCCIÓN EN LA ETAPA DE ACABADOS - ARQUITECTURA EN PERÚ EN EL AÑO DE 2019
| dc.contributor.author | Miranda Mejia, Maykol | |
| dc.contributor.author | Torobisco Vilca, Esmeralda | |
| dc.contributor.author | Gomez Minaya, Rosmery | |
| dc.coverage.spatial | Bolivia | |
| dc.date.accessioned | 2026-03-23T15:45:02Z | |
| dc.date.available | 2026-03-23T15:45:02Z | |
| dc.date.issued | 2020 | |
| dc.description | Vol. 20, No. 1 | |
| dc.description.abstract | En una ciudad emergente debido al dinamismo económico, con una capital que en los últimos años ha tenido un crecimiento demográfico agigantado, demanda proyectos inmobiliarios para satisfacer a los nuevos núcleos familiares. Como es el caso de los edificios multifamiliares de mediana envergadura, para los que se encontraron aplicaciones de nuevas metodologías como el Last Planner System que reduce los tiempos de ejecución. Para ello, el presente trabajo analiza, desarrolla e implementar mecanismos basados en la Filosofía Last Planner System, aplicados a un proyecto de edificación de 5 pisos, centrándose en las partidas de Acabados en un periodo de 5 semanas. Para completar esa cifra fue necesario crear 3 sectores luego se realizó un Plan Intermedio (Look Ahead Planning), posteriormente un Plan Semanal. En el presente estudio se implementó la metodología LPS en una obra de mediana envergadura a diferencia de otros estudios similares como el de (Miranda Casanova, 2012). Se concluye en el presente estudio de la aplicación del LPS a un proyecto mediano, es eficaz respecto a la mejora en los tiempos de ejecución con un valor de porcentaje de eficacia de 76 % para la ejecución de las partidas de Arquitectura. | es |
| dc.description.abstract | In an emerging city due to economic dynamism, with a capital that in recent years has had an enormous population growth; it demands real estate projects to satisfy the new family nuclei. As is the case of medium-sized multi-family buildings, for which applications of new methodologies such as the Last Planner System which reduces execution times were found. For this, the present work analyzes, develops and implements mechanisms based on the Last Planner System Philosophy, applied to a 5-story building project, focusing on the Finishing items in a period of 5 weeks. To complete this figure, it was necessary to create 3 sectors, and then an Intermediate Plan (Look Ahead Planning) was made, then a Weekly Plan. In the present study, the LPS methodology was implemented in a medium-sized work unlike other similar studies such as (Miranda Casanova, 2012). It is concluded in the present study of the application of the LPS to a medium-sized project, it is effective with respect to the improvement in the execution times with a 76% efficiency value for the execution of the Architecture items. | en |
| dc.identifier.uri | http://www.scielo.org.bo/scielo.php?script=sci_arttext&pid=S2518-44312020000100014&tlng=es | |
| dc.identifier.uri | https://andeanlibrary.org/handle/123456789/94430 | |
| dc.language.iso | es | |
| dc.publisher | Inv. y Des. | |
| dc.relation | http://www.scielo.org.bo/pdf/riyd/v20n1/v20n1_a14.pdf | |
| dc.relation.ispartof | Inv. y Des. | |
| dc.source | SciELO Bolivia | |
| dc.subject | Acabados | |
| dc.subject | Envergadura | |
| dc.subject | LPS | |
| dc.subject | Eficaz | |
| dc.subject | Tiempo | |
| dc.subject | Finishes | |
| dc.subject | Wingspan | |
| dc.subject | LPS | |
| dc.subject | Effective | |
| dc.subject | Time | |
| dc.title | EVALUACIÓN DE LA EFICACIA DE LA APLICACIÓN DE LAST PLANNER SYSTEM EN UN PROYECTO DE CONSTRUCCIÓN EN LA ETAPA DE ACABADOS - ARQUITECTURA EN PERÚ EN EL AÑO DE 2019 | |
| dc.title.alternative | EVALUATION OF THE EFFECTIVENESS OF THE LAST PLANNER SYSTEM APPLICATION IN A CONSTRUCTION PROJECT IN THE FINISHING STAGE - ARCHITECTURE IN PERU IN THE YEAR OF 2019 | |
| dc.type | Artículo Científico Publicado |