PROGRAMACIÓN DE LA CONSTRUCCIÓN DEL TERCER ANILLO DE MUROS ANCLADOS DE UNA EDIFICACIÓN APLICANDO EL MÉTODO DE LÍNEAS DE BALANCE

dc.contributor.authorParedes Gutierrez, Steven
dc.contributor.authorTorres Tacuri, Hubert
dc.contributor.authorGómez Minaya, Rosmery
dc.coverage.spatialBolivia
dc.date.accessioned2026-03-23T15:45:00Z
dc.date.available2026-03-23T15:45:00Z
dc.date.issued2020
dc.descriptionVol. 20, No. 1
dc.description.abstractEn la industria de la construcción, planificar y controlar el cronograma de obra son importantes, debido a que se cometen errores al realizar la programación inicial del proyecto, ya que durante la ejecución de la obra se generan retrasos entre actividades al usar métodos convencionales como CPM y PERT por una ineficiente gestión del tiempo. Este trabajo de investigación determina los beneficios en la gestión del tiempo al aplicar la programación por Líneas de Balance (LDB), en la construcción de muros anclados del tercer anillo de una edificación, dado que este método facilita la visualización de actividades en el cronograma, lo que ayuda a identificar los conflictos entre las tareas antes de que estos se realicen. Se analiza las velocidades y rendimientos, de datos obtenidos de los cronogramas real y meta llevados a cabo con el método de LDB, para analizar la diferencia de velocidades representándolo en porcentajes, donde se evalúa aquellos sectores y partidas que generan retrasos o adelantos en el cronograma. Con base en los resultados obtenidos, el método LDB mejora la gestión del tiempo en 3.57% con relación a las velocidades de avance, empleando mejoras en el ratio y mano de obra a través del control del cronograma por porcentajes de avance de las actividades relativo a lo planificado. Además, se implementa un diagrama de flujo para una mejor aplicación de las LDB, en el control del proceso de las actividades de muros anclados, esto a diferencia de otros estudios previos realizados.es
dc.description.abstractIn the construction industry, planning and controlling the construction schedule are important, because mistakes are made in the initial scheduling of the project, as during the execution of the work delays are generated between activities using conventional methods such as CPM and PERT by inefficient time management. In this research work, the benefits in time management were determined by applying the programming by Balance Lines (LOB), in the construction of anchored walls of the third ring of a building, given that this method facilitates the visualization of activities in the schedule, which helps to identify conflicts between tasks before they are performed. We analyzed the velocities and yields of data obtained from the real and target schedules carried out with the LOB method, to analyze the difference in velocities representing it in percentages, where we evaluated those sectors and activities that generate delays or advances in the schedule. Based on the results obtained, the LOB method improved time management by 3.57% in relation to velocities, employing improvements in the ratio and labor through the control of the schedule by percentages of progress of the activities relative to what was planned. In addition, a flow chart was implemented for a better application of the LOB, in the control of the process of the activities of anchored walls, this unlike previous studies.en
dc.identifier.urihttp://www.scielo.org.bo/scielo.php?script=sci_arttext&pid=S2518-44312020000100013&tlng=es
dc.identifier.urihttps://andeanlibrary.org/handle/123456789/94427
dc.language.isoes
dc.publisherInv. y Des.
dc.relationhttp://www.scielo.org.bo/pdf/riyd/v20n1/v20n1_a13.pdf
dc.relation.ispartofInv. y Des.
dc.sourceSciELO Bolivia
dc.subjectLíneas
dc.subjectBalance
dc.subjectLDB
dc.subjectCronograma
dc.subjectTiempo
dc.subjectPlanificar
dc.subjectControlar
dc.subjectLine
dc.subjectBalancing
dc.subjectLOB
dc.subjectSchedule
dc.subjectTime
dc.subjectTo Plane
dc.subjectControl
dc.titlePROGRAMACIÓN DE LA CONSTRUCCIÓN DEL TERCER ANILLO DE MUROS ANCLADOS DE UNA EDIFICACIÓN APLICANDO EL MÉTODO DE LÍNEAS DE BALANCE
dc.title.alternativePROGRAMMING OF THE CONSTRUCTION OF THE THIRD RING OF ANCHORED WALLS OF A BUILDING APPLYING THE BALANCING LINES METHOD
dc.typeArtículo Científico Publicado